Non-Responsiveness and Non-Responsibility: The Difference and Why It Matters
November 8th, 2011As to non-responsiveness and non-responsibility, the difference is in the details. Despite the likely easy confusion between the two due to the similar spellings, the difference between the two is important and can alter the remedy available to a bid protester. This point is illustrated in Matter of: Tessa Structures, LLC (“Matter of Tessa”).
On May 26, 2004, the Department of Transportation (“DOT”) issued an Invitation for Bids (“IFB”) for a fixed-priced contract requiring bridge-related repairs. The IFB stated that the award would be based on the lowest total project price, which would be the sum of the bid price and the contract administrative costs associated with the length of the performance period stated in the bid ($2,200 per calendar day bid). Matter of Tessa, at *1. The IFB set out a maximum performance period of 305 days, but the IFB provided no minimum performance period.
Three bids were timely submitted. Tessa Structures, LLC (“Tessa”) submitted the lowest evaluated price of $2,542,730 based on a bid of $2,278,730 and a performance period of 120 days. Fort Myer’s submitted the second lowest evaluated price of $2,546,430 based on a bid of $1,996,430 and a performance period of 250 days.
DOT responded to Tessa’s bid by letter, informing Tessa that the agency was “very concerned” with the brevity of Tessa’s 120-day performance period submitted in its bid. Id. at *2. The letter noted that the agency had estimated a significantly longer performance period and, therefore, requested that Tessa submit a construction schedule explaining how it expected to complete the work on-time. Tessa submitted a timely response which included, among other required information, an estimated start date of August 28.
DOT replied to Tessa’s letter stating that Tessa’s suggested start date of August 28 was contrary to the requirements of the IFB. Tessa again responded by letter to the agency explaining that the IFB did not preclude a start date of August 28, and, in the alternative, even with a later start date, it could still complete the work on-time. Finally, in response to Tessa’s letter, DOT informed Tessa that it was rejecting Tessa’s bid as non-responsive. The letter stated Tessa had failed to adequately address the agency’s concerns regarding its 120-day proposed work schedule. Tessa filed a timely bid protest.
In its protest, Tessa asserted that its bid complied with all contract requirements and, therefore, was responsive. Tessa further asserted that if the agency had concerns with its proposed work schedule, the agency should have instead made a finding of non-responsibility – not non-responsiveness. Responsiveness concerns whether a bidder has unequivocally promised, as shown on the face of its bid, to provide the items or services called for by the material terms of the IFB. Id. at *3. Responsibility, on the other hand, concerns whether a bidder can perform as promised in its bid. Id. Because Tessa’s bid, on its face, met the services required by the IFB, Tessa’s bid was responsive. The agency’s concerns regarding Tessa’s proposed work schedule affect Tessa’s bid responsibility.
Because Tessa was considered a small business, the difference in the determination was important. An agency finding of non-responsiveness allows that agency to reject the bid; however, an agency finding of non-responsibility allows a small business, such as Tessa, to challenge that agency’s finding through the Small Business Administration (“SBA”) certificate of competency (“COC”) procedures.
Accordingly, Tessa’s bid protest was sustained by the Comptroller General. For Tessa’s remedy, the General required DOT to refer its determination to SBA for review under COC procedures. Further, the General awarded Tessa reimbursement of its protest costs, including reasonable attorneys’ fees. See 4 C.F.R. § 21.8(f)(1).
For a copy of the opinion in Matter of Tessa, please visit http://www.gao.gov/decisions/bidpro/298835.htm.
